Water fee may reach NOK 47,500 without state money
Published

The yearly water fee for a Longyearbyen home of 120 m² may rise from NOK 17,000 to NOK 47,500 if the state pays nothing towards a new water supply, the local council (Longyearbyen lokalstyre) said. The estimate is in a council report dated Thursday 19 November. The administration committee (Administrasjonsutvalget) takes up the matter on Wednesday 25 November at 10:00 Svalbard time.
With the state paying half of the investment, the council put the fee at NOK 35,100 a year. If the state paid all of it, the fee would still rise, to NOK 22,900, because new plants cost more to run. The council said that the figures were estimates and not calculated future fee rates.
The water fee may rise from NOK 17,000 to as much as NOK 47,500
Åsmund Sandvik, the council's chief administrative officer, said in the report that the project would probably have to stop without enough state money. The fees would then be too high for residents and businesses, he said.
Sandvik recommended starting the pre-project while the council works to secure state funding. Waiting for an answer would delay the needed upgrade of the water supply and the creation of a backup supply, he said.
The proposal is the one the council presented on Thursday 19 November. It keeps Isdammen as the main water source, with better water treatment. It also covers work on the distribution system and a desalination plant at Hotellneset as a full backup supply.
The council said that this was not a decision to build, and that each investment would come back to the politicians.
The council put the pre-project at NOK 55.6 million on Thursday 19 November, with NOK 39.7 million of it in 2027. The council's report gave NOK 11.1 million for 2028 and NOK 4.8 million for 2029.
The main supply takes NOK 20.3 million of the total and the backup supply NOK 18.0 million. The distribution system takes NOK 14.6 million and shared project costs NOK 2.7 million.
The proposal is to borrow the 2027 amount to the extent that state grants do not cover it. Under the proposal, the pre-project would not raise the water fee in 2027.
The council said that its preliminary timetable had investment decisions for the main supply and the distribution system in 2027 to 2028, with the work running towards 2030. For the backup supply, it had the investment decision in 2029 to 2030, with the work running towards 2033.
The study behind the proposal also recommended a quick alternative way to produce emergency drinking water, for example a small desalination plant. A closer assessment has been ordered, and a basis for a decision is planned for the first quarter of 2027, the council said.
The study put the later building at NOK 623 million at 2026 prices, the council said on Thursday 19 November. The figure is the sum of the estimates for the three parts. The council called the figures preliminary and said that the uncertainty was considerable.
The council said that the water in the ordinary pipe network had not met the health-based limits of the drinking water regulations since September 2025.
The case goes next to the technical, environment and business committee (Teknisk-, miljø- og næringsutvalget) on Tuesday 1 December. The local council is to take it up on Wednesday 9 December. The administration committee also has the budget and economic plan for 2027 to 2030 on its list on Wednesday 25 November.
Written by the editor with the Wire's software, from the sources listed below, and checked against them before publication. The editor answers for every story. How the Wire is made.
Sources
Longyearbyen lokalstyre (the local council)
New water supply in Longyearbyen: choice of concept and passing of decision point 1 (case 56/26)
Meeting notice, the administration committee, 25 November 2026
Study recommends new solution for water supply
How the chief administrative officer wants to prioritise in 2027
History: The last boat of 1945 turns back off Isfjorden
- Study backs Isdammen as water source for Longyearbyen (19 November 2026)
- Budget plan expects grants to pay for new water supply (10 November 2026)
- State points to budget process for Longyearbyen water (29 October 2026)
- Jensen asks if state will fund Longyearbyen water fix (26 October 2026)
- Council still advises against drinking tap water in Longyearbyen; water supply decision due in December (26 October 2026)
- Longyearbyen council to choose water supply concept in December (13 October 2026)
- Concept choice for water supply to be decided in December (21 October 2026)
Svalbard